October 2011

DESIGN:
Design is complete.
RIGHT-OF-WAY:
Right-of-way acquisition is complete.
UTILITIES:
Utility design is complete. Waterline and overhead utility relocations along Rolling Road and Fairfax County Parkway began March 2011.
PERMITS:
Environmental permitting is complete.
CONSTRUCTION:
Erection of abutments and piers for the Rolling Road bridge are complete. Construction of the bridge super structure is underway. Utility relocations are ongoing. Storm Drainage installation is ongoing. Relocated section of Hooes Road and new ramp are open. Southbound section of parkway is underway.

 

 

 

 

 

 

 

 

 